TIMELINE

Overview

  • January 2013: Environmental Assessment Certificate issued
  • May - August 2013: Provincial and federal permits issued
  • August - December 2013: Clearing project area and conduct investigative works
  • Spring 2014 - Spring 2017: Civil construction
  • 2016: Completion of the ULHP transmission line
  • 2017: Completion of Boulder Creek and Upper Lillooet River hydroelectric facilities
 